Operations

200-acre township delivery — phase progress, milestone tracking, contractor performance and cost control.

4,510 Cr sanctioned

Overall Completion

59%

+4 ptsweighted by value

Budget Utilised

54%

+3 pts₹2429 Cr of ₹4510 Cr

Milestones On Track

18 / 24

+2next 90 days

Open Snags

412

-86Phase 1 & 2

Phase timelines & cost

Phase 1 — Towers 1-6

Handed Over

Delivered Mar 2025

Construction progress100%
Cost utilised704 Cr / ₹720 Cr

Phase 2 — Towers 7-14

On Track

Dec 2026

Construction progress82%
Cost utilised921 Cr / ₹1140 Cr

Phase 3 — Towers 15-20

At Risk

Jun 2028

Construction progress34%
Cost utilised502 Cr / ₹1480 Cr

Clubhouse (7.5 Acres)

On Track

Sep 2027

Construction progress61%
Cost utilised128 Cr / ₹210 Cr

Commercial Zone (25 Acres)

Delayed

Mar 2029

Construction progress18%
Cost utilised174 Cr / ₹960 Cr

Upcoming milestones

Next 90 days

  • Tower 12 — Slab 28 casting

    04 Aug 2026 · L&T

    On Track
  • Phase 3 excavation completion

    21 Aug 2026 · Shapoorji

    At Risk
  • Clubhouse MEP first fix

    09 Sep 2026 · Voltas

    On Track
  • Tower 9 external plastering

    30 Sep 2026 · L&T

    Delayed
  • STP commissioning — Zone B

    18 Oct 2026 · Ion Exchange

    On Track

Risk register

RiskAreaImpactMitigation
Sand & aggregate supply disruptionPhase 3HighDual-vendor contract signed
Labour shortage post-monsoonClubhouseMediumContract labour buffer 12%
Commercial zone approval delayCommercialHighBBMP liaison escalation