Operations
200-acre township delivery — phase progress, milestone tracking, contractor performance and cost control.
₹4,510 Cr sanctioned
Overall Completion
59%
+4 ptsweighted by value
Budget Utilised
54%
+3 pts₹2429 Cr of ₹4510 Cr
Milestones On Track
18 / 24
+2next 90 days
Open Snags
412
-86Phase 1 & 2
Phase timelines & cost
Phase 1 — Towers 1-6
Handed OverDelivered Mar 2025
Construction progress100%
Cost utilised₹704 Cr / ₹720 Cr
Phase 2 — Towers 7-14
On TrackDec 2026
Construction progress82%
Cost utilised₹921 Cr / ₹1140 Cr
Phase 3 — Towers 15-20
At RiskJun 2028
Construction progress34%
Cost utilised₹502 Cr / ₹1480 Cr
Clubhouse (7.5 Acres)
On TrackSep 2027
Construction progress61%
Cost utilised₹128 Cr / ₹210 Cr
Commercial Zone (25 Acres)
DelayedMar 2029
Construction progress18%
Cost utilised₹174 Cr / ₹960 Cr
Upcoming milestones
Next 90 days
- On Track
Tower 12 — Slab 28 casting
04 Aug 2026 · L&T
- At Risk
Phase 3 excavation completion
21 Aug 2026 · Shapoorji
- On Track
Clubhouse MEP first fix
09 Sep 2026 · Voltas
- Delayed
Tower 9 external plastering
30 Sep 2026 · L&T
- On Track
STP commissioning — Zone B
18 Oct 2026 · Ion Exchange
Risk register
| Risk | Area | Impact | Mitigation |
|---|---|---|---|
| Sand & aggregate supply disruption | Phase 3 | High | Dual-vendor contract signed |
| Labour shortage post-monsoon | Clubhouse | Medium | Contract labour buffer 12% |
| Commercial zone approval delay | Commercial | High | BBMP liaison escalation |